Senoko Power Station
Name officialSenoko Power Station
Coordinates1°28′N 103°48′E
CountrySingapore
LocationSenoko, Sembawang
StatusO
Commissioned1976
CostSGD 1.2 billion
OwnerLion Power Holdings (Senoko Energy)
Th fuel primaryNatural gas
Th fuel secondaryFuel Oil
Th fuel tertiaryNone
Ps units operational7
Ps units manu modelHitachi Deregistered
Siemens
Alstom
MHI
Ps cogenerationNo
Ps combined cycleYes
Ps electrical capacity2800 MW (authorised)
Websitesenokoenergy.com
Extra2x Hitachi Thermal power plant has been Deregistered since 2018 and is scheduled for decommission.

The Senoko Power Station is the largest power station in Singapore. It is located in Senoko, Sembawang and was commissioned in 1976. It is owned by Senoko Energy Pte Ltd, formerly known as Senoko Power Ltd.

Description

The Senoko Power Station is located at a former British Naval Base in Sembawang, Singapore.[1]

The Steam Plant Stage I, which was completed in 1976, comprised three steam thermal plants with 120 MW of capacity each. The Steam Plant Stage II, which was completed in 1979, comprised three steam thermal plants with 250 MW of capacity each. The Steam Plant Stage III which was completed in 1983 comprises another two steam thermal plants with 250 MW of capacity each. In 1992, Stage III 250 MW boilers were modified with gas burners to enable it to fire both Natural Gas and Fuel Oil.

In the 1990s, it was converted from a gas turbine power plant to a combined cycle plant.[2] The combined cycle plants include combined cycle plants 1 and 2, combined cycle plants 3 to 5 and combined cycle plants 6 and 7. The Gas Plant Stage I was an open cycle plant with 4 open cycle gas turbines with 131 MW capacity when commissioned in 1991. In 1994, the 4 open cycle gas turbines were converted into two blocks of combined cycle plants with 425 MW of capacity each and renamed CCP 1 and 2. In 2010, Gas Turbine GT22 of CCP 2 was upgraded with new vanes and blades for its stage 1 and 2

The combined cycle plants 3 to 5 were completed and fully operational by 2004 with 365 MW of capacity each, which involved the repowering of the Stage I oil-fired steam thermal plant. The combined cycle plants 6 and 7 were completed and commissioned by 2012 with 431 MW of capacity each, which involved the repowering of the Stage II oil-fired steam thermal plant.

In its early years, the plant used crude oil as fuel to power its turbines; however, this was replaced by natural gas piped from Terengganu on the east coast of Peninsular Malaysia after 1992. Oil, however, is still used as a back-up.

History

The Senoko Power Station originally began operations in 1976.[3] It was built by PUB with plans starting as early as 1971.[1] Two additional stages of construction were conducted with it being officially completed in 1983 as Singapore's largest power station.[1]

In the 1990s, the Senoko Power Station was converted from an open-cycle gas turbine power plant to Singapore's first combined cycle plant.[2]

In 1992, a fire broke out at one of its plants resulting in a major power outage in the island.[4]

Based on a mutual agreement between Malaysia and Singapore on electricity, the plant is linked by a submarine cable to the Sultan Iskandar Power Station in Pasir Gudang, Johor. In the event of a power outage in Peninsular Malaysia, the plant would supply electricity to the Johor plant. Likewise, if there is a power outage in Singapore, the Johor plant would supply electricity to Senoko.

The plant's only standing concrete chimney which belongs to Stage 3, at 182 metres high, is the tallest structure in the northern part of Singapore and one of the tallest structures on the island. It is clearly visible across the Tebrau Straits and in most parts of Johor Bahru. The plant's second chimney which belongs to Stage 2 was demolished in July 2010 as part of the repowering process.

On 5 September 2008, Temasek Holdings sold Senoko Energy Pte Ltd to Lion Power Holdings for S$3.65 billion. Lion Power is owned by a consortium led by Japan's Marubeni Corporation. Other members of the consortium are GDF Suez of France, The Kansai Electric Power Company, Kyūshū Electric Power Company and Japan Bank for International Cooperation.[5]

Plant development stageCommission dateStatusInstallation cost (in S$)CapacityPlant typeTurbine manufacturer
Steam Stage I1976Decommissioned
Repowered to CCP 3 – 5
600,000,0003 x 120 MWSteam Thermal PlantHitachi
Steam Stage II

October 1978 April 1979

September 1979

Decommissioned Repowered to CCP 6 – 7600,000,0003 x 250 MWSteam Thermal PlantHitachi
Steam Stage IIIJune 1983
November 1983
Operational400,000,0002 x 250 MWSteam Thermal PlantHitachi
Gas Stage I1990
1991

Upgraded to

CCP 1 & 2

4 x 131 MWOpen Cycle PlantSiemens
CCP 1 & 21994Operational2 x 425 MWCombined-Cycle PlantSiemens
CCP 3 – 5February 2002
July 2004
December 2004
Operational3 x 365 MWCombined-Cycle PlantAlstom
CCP 6 – 72012Operational1,000,000,0002 x 431 MWCombined-Cycle PlantMHI

References

  1. ^ "Senoko Power Station Opens". History SG. Retrieved 6 February 2020.
  2. ^ "Environmental innovations seen in 1997 Project of the Year winners". Power Engineering International. 1 November 1997. Retrieved 6 February 2020.
  3. ^ Global Water Security: Lessons Learnt and Long-Term Implications. Springer. 2018. ISBN 9789811079139. Retrieved 6 February 2020.
  4. ^ "1992". Retrieved 28 November 2018.
  5. ^ Nicholas Fang (5 September 2008). "Temasek sells Senoko Power to Marubeni-led group for S$3.65b". Channel NewsAsia. Retrieved 5 September 2008.