North–South Commuter Railway
SystemPhilippine National Railways
StatusValenzuela to Clark and Manila to Calamba segments: Under construction
Valenzuela to Solis segment: Construction pending
Locale
ContinuesfromPNR Metro Commuter Line (Solis to Calamba only)
Stations36
Routes4
YearcommencedFebruary 15, 2019 (age 7)
PlanopenDecember 2027 (partial)
January 2032 (full)[note 1]
OwnerDepartment of Transportation
OperatorPhilippine National Railways
DepotMalanday[note 2]
Mabalacat
Banlic
CharacterElevated[note 3]
StockVarious, see rolling stock
Linelength147 km
TracksDouble[note 4]
Speed
  • Commuter:
  • 120 km/h (75 mph)
  • Airport Express:
  • 160 km/h (100 mph)
SignallingHitachi Rail STS/Alstom Atlas 200 ETCS-2[note 5]
Electrificationoverhead lines[1]
Load gauge4,150 × 3,000 mm (13 ft 7 in × 9 ft 10 in)[1]
MinradiusMainline: 260–400 m (850–1,310 ft)[1]
Depot: 92–100 m (302–328 ft)[1]
Elevation130 m (430 ft) at Clark International Airport station
Maxincline25
Aveinterstation4.11 km (2.55 mi)
Websitehttps://nscr.com.ph

The North–South Commuter Railway[note 6] (NSCR), also known as the Clark–Calamba Railway, is a 147-kilometer (91-mile) commuter rail system under construction on the island of Luzon in the Philippines. Running from New Clark City in Capas, Tarlac, to Calamba, Laguna, with 36 stations and four services, the railway is designed to improve connectivity within the Greater Manila Area and will be integrated with the railway network in the region.[2][3][4]

Originally planned in the 1990s, the railway project has had a tumultuous history, being repeatedly halted and restarted for various reasons.[5] The first proposals were the 32-kilometer (20-mile) "Manila–Clark rapid railway" with Spain in the 1990s, alongside the "Manila–Calabarzon Express".[5][6][7] During the 2000s, the Northrail project with China was initiated but discontinued in 2011 due to allegations of overpricing.[8][9][10][11] The railway's current incarnation began development in 2013.[12] The project's initial phase was approved in 2015,[13] and construction began in 2019.[14]

Expected to cost ,[15] the line is the most expensive railway transportation project in the country. The entire system is expected to be completed by January 2032.[16]

History

Background

Comparison between NSCR and its predecessor projects[17]
SegmentMMUTISNorthrailNSCR
Calamba–CaloocanManila–Calabarzon Express (MCX)[note 7]PNR Clark
PNR Calamba
Fort Bonifacio–CaloocanManila–Clark Rapid Railway System (MCRRS)Phase 1Phase 3
Caloocan–MalolosPhase 1PNR Clark
Malolos–Clark
Clark–San FernandoPhase 3Phase 4rowspan="2" [note 8]
San Fernando–LaoagPhase 4
Subic spurPhase 2Phase 2[note 9]
San Jose spurPhase 4[note 10]

During the Spanish and American colonial periods, the Manila Railway Company, later the Manila Railroad Company (MRR), operated various local trains between Manila and its neighboring provinces. By the 1920s, trains had run from Tutuban to Naic in Cavite, Pagsanjan in Laguna, Montalban in Rizal, and Bulacan.[18] The network was heavily damaged in the Battle of Manila during World War II,[19] but was mostly reestablished after the war.[20] MRR was succeeded by the Philippine National Railways (PNR) on June 20, 1964.[21]

On April 6, 1970, PNR inaugurated the Metro Manila Commuter Service, which started at Manila North Harbor and ended in Biñan station in Laguna.[22] After numerous expansions, the commuter service served thousands of daily riders in its system and had an expansive network in and out of Metro Manila.[23] In 1978, at the request of the Philippine government, the Japan International Cooperation Agency (JICA) conducted a study on the electrification of the commuter service.[24] The plan was made to keep up with the increasing demand for transportation in the region. It called for the replacement of the diesel-run trains and the electrification of the PNR commuter line. Two experts from the Japanese National Railways were sent to conduct the study.[24]

Services north of Manila started to decline in the 1980s. However, commuter services were briefly extended to Malolos starting in 1990 under the Metrotren project but later ceased in 1997.[25] Since then, railway services have been mostly confined to the south, with the contemporary Metro Commuter Line being predominantly aligned to the South Main Line.[26]

Proposals in the 1990s

In 1994, President Fidel Ramos signed an executive order designating Clark Air Base, as the premier international airport, with the support of the Bases Conversion and Development Authority (BCDA), while the other agencies also supported the development, and in the same year, President Ramos signed a memorandum of agreement with Juan Carlos I of Spain for the construction of a railway line from Manila to Clark.[27][5] This would be known as the Manila–Clark rapid railway system (MCRRS). A joint venture agreement was entered into on June 10, 1995, between BCDA, PNR, Philippine companies DMCI Holdings and Fort Bonifacio Development Corporation, and Spanish firms with Construcciones y Auxiliar de Ferrocarriles, Entrecanales y Tavora, Cubiertas y MZOV, (both companies later merged to form Acciona) and Cobra Instalaciones y Servicios, S.A., as well as other investors. The agreement also established the North Luzon Railways Corporation (NLRC) for the purpose of constructing, operating, and managing the railroad system on August 24.[5][28][29] In 1996, Spanish and Japanese companies entered the bidding process, while the project would have also been co-financed by the Overseas Economic Cooperation Fund (OECF, later Japan Bank for International Cooperation or JBIC, now JICA). The NLRC then entered into an engineering, procurement and construction contract with the Spanish Railways Corporation on February 7 of the same year. Meanwhile, in 1997, Ayala Land proposed the construction of a railway known as the Manila–Calabarzon Express (MCX). Its initial phase involved the rehabilitation of the railway from Caloocan to Calamba and eventually the construction of spur lines to Carmona and Canlubang under a build–own–operate scheme.[5][30][31]

Studies indicated that the MCRRS project was planned to unfold in four phases.[17] Phase 1, was set to connect Fort Bonifacio, including a proposed intermodal station in Bonifacio Global City, to the Clark Freeport and Special Economic Zone. Phase 2 aimed to extend the line to Subic Bay. Phase 3 planned for an extension to San Fernando, La Union. Phase 4 proposed another extension from San Fernando to Laoag and an additional spur line to San Jose, Nueva Ecija.[17] Both proposals were subsequently included in the Metro Manila Urban Transportation Integration Study (MMUTIS).[7]

The contract between the NLRC and the Spanish Railways Corporation was terminated on August 14, 1998, after the parties disagreed on the source of funding for the project.[5]

Despite the contract termination, in September 1999, the National Economic and Development Authority (NEDA) approved the MCRRS, with the initial phase covering a segment from Caloocan to Calumpit. The source of funding was to be the Obuchi Fund from the JBIC.[5] The consortium was also now joined by Japanese companies including Fil Estate Management, Nishimatsu Construction, and Mitsui & Co.[32] Pre-construction activities such as right-of-way clearing and relocation of affected informal settlers began, but a presidential directive later halted the clearing activities.[5] Then, JBIC later dumped the project because of the government could not commit to clear the railway path squatters before releasing a loan, causing a lack of funds.[33]

Ayala Land was subsequently excluded from the MCX as the government opted to fund the railway construction also through the Obuchi Fund, opening the project for bidding to private developers.[34][35] In April 2000, the JBIC Obuchi Fund provided a $300 million loan to tap the ₱18.2 billion project. By the following year, the Japanese government was considering funding the project.[36][37]

Another study about the integration of Metro Manila's railway network by JICA in 2001 proposed the through-operation of both railways in two options, such as an elevated section running 10 kilometers (6.2 mi) on the existing PNR old right-of-way or an underground section running 7 kilometers (4.3 mi) from Tayuman to Vito Cruz. According to SIRNMM, the proposed indicative length, which would have run from Tayuman to Marilao, was 17.0 kilometers (10.6 mi), while both options for MCX were to be 46.2 kilometers (28.7 mi) (elevated) or 43.2 kilometers (26.8 mi) (underground) from Tayuman to Cabuyao.[38][39] However, the plans would never materialize.

Northrail

Under the presidency of Gloria Macapagal Arroyo, the MCRRS was succeeded by the Northrail project, a 320-kilometer (200-mile) railway system from Caloocan to San Fernando, La Union.[40] The Northrail project's 80-kilometer (50-mile) phase 1 involved the upgrading of the existing single track to an elevated dual-track system, converting the rail gauge from narrow gauge to standard gauge, and linking Manila to Malolos in Bulacan and further on to the Clark Freeport and Special Economic Zone and Clark International Airport.[41][5] The first segment of phase 1 covered the 32-kilometer (20-mile) railway from Caloocan to Malolos.[42] Succeeding phases followed the MCRRS masterplan, although Phase 4 was removed, Phase 3 was rebranded as Phase 4, and the section between Fort Bonifacio to Caloocan was rebranded as Phase 3, while Phase 2 was unchanged.[17] Its southern counterpart, the Southrail project, involved the rehabilitation of the entire South Main Line from Calamba to Legazpi, Albay, with an extension to Matnog.[43][44] Meanwhile, the Northrail–Southrail Linkage involved the rehabilitation of the existing Metro Commuter Line from Caloocan to Calamba, creating a link between the two systems.

On September 14, 2002, a memorandum of understanding was signed by NLRC and China National Machinery and Equipment Group (CNMEG) for the project.[5] It was later approved on August 5, 2003.[5] The project was estimated to cost around US$500 million, and the funding was to be covered by a US$400 million loan from the Export–Import Bank of China, and the rest to be shouldered by the government through BCDA and NLRC.[5][6][42] The Southrail project was also expected to be financed by loans from China,[45][46] while the linkage project was to be financed by South Korea.[47][48] While the plans for Southrail were not realized, the initial phase of the linkage project from Caloocan to Alabang was completed in December 2010.[49]

Before Northrail's construction could start, the project became embroiled in controversy as the Philippine Senate raised concerns about alleged corruption in the project. Senator Franklin Drilon commissioned a study from the University of the Philippines, which recommended the cancellation of the railway's construction, citing anomalies in the bidding process and the Buyer Credit Loan Agreement (BCLA) with Exim China.[5] Despite the controversy, preparatory construction began in early November 2006.[50] Civil and design works started in October 2007.[5] However, CNMEG reportedly demobilized from the project on July 1, 2008, due to differences on engineering and construction standards, although this was later retracted.[5]

Due to delays in the construction work, it was soon renegotiated with the Chinese government. Construction temporarily continued in January 2009 with the support of the North Luzon Railways Corporation.[5] However, the project would be shelved in March 2010 due to persisting legal issues and allegations of overpricing and corruption.[51][41] In 2011, Northrail was cancelled by the government under the presidency of Benigno Aquino III.[50][52] Like the failed Hopewell Project in Bangkok, a few structures had been completed by the time of its cancellation. The government contemplated reusing the completed structures from the project, but ultimately, this was not implemented.[53]

In September 2011, the government expressed its interest to restart the project with China reportedly open to reconfigure the project.[51][54] In March 2012, the Philippine Supreme Court authorized a lower court to hear the case for voiding the contract. Instead of paying the US$184 million owed by the government in 2012, the Department of Finance was to pay Exim China four installments of US$46 million from September 2012 onwards.[52] In August 2012, the Chinese and Philippine governments agreed to "disengage" from the project,[55] although the Philippine government was still obligated to pay the corresponding loans. On November 6, 2017, DOTr, BCDA, and NLRC reached an out-of-court settlement with Sinomach (formerly CNMEG), resolving the five-year dispute. It saved the government in potential payment of claims to Sinomach and hundreds of millions of pesos in legal fees and arbitration costs.[41]

The Governance Commission for GOCCs (GCG) ordered the deactivation of NLRC in May 2019. According to GCG, the company was "not producing the desired outcomes, no longer achieving the objectives and purposes for which it was designed and created, and not cost efficient and does not generate the level of social, physical and economic returns vis-à-vis the resource inputs."[56] On October 19, 2023, NLRC was formally abolished, with the BCDA to act as the administrator and liquidator of NLRC and settle its liabilities.[57]

Development

With the termination of the Northrail project, the Department of Transportation and Communications considered restarting the project by commissioning a feasibility study by CPCS Transcom Ltd. of Canada. Part of the study examined having a Malolos–Tutuban–Calamba–Los Baños commuter line.[58][59] The feasibility study was still ongoing when the NEDA included the project in the Metro Manila Dream Plan, which it approved in 2014.[60] JICA also conducted a new study a year before a new transport infrastructure master plan was published. This plan calls for an airport express railway linking Ninoy Aquino International Airport in Metro Manila to Clark International Airport with a total length of 99.4 kilometers (61.8 mi).[17] The government also examined building a railway on top of the North Luzon Expressway instead of using the PNR right of way, which was still allocated for the Northrail project at the time.[61]

By August 2014, the Northrail project was reinitiated as the North–South Commuter Railway (NSCR) and awaited approval.[52] On February 16, 2015, the NEDA board, chaired by President Aquino, approved the NSCR Phase 1 as part of the North–South Railway Project (NSRP).[62][63] The NSCR, a part of the NSRP north line's first phase, was a 37-kilometer (23-mile) electrified narrow gauge commuter railway from Tutuban to Malolos, funded through overseas development assistance.[64][65] Other components of NSRP masterplan include the reconstruction of the existing Metro Commuter line and the reestablishment of long-haul services to northern and southern Luzon, all of which were to be funded through a public–private partnership (PPP) scheme.[65][62][66] After President Aquino met with Japanese Prime Minister Shinzo Abe in Japan in June 2015, Abe expressed his commitment to fund the project. On November 19, 2015, representatives of both countries exchanged notes on the project in the presence of Abe and Aquino.[13] JICA was chosen by the Japanese government to look into financing the project, and on November 27, JICA and the Department of Finance signed a loan agreement worth ₱97.3 billion ($1.99 billion) for the financing of the first phase.[67][68][69]

Before the inauguration of President Rodrigo Duterte, Aquino's successor, Chinese diplomats reportedly offered to construct the railway from Manila to Clark within two years.[70] However, his administration continued the NSCR project with Japan and included the project under its flagship Build! Build! Build! Infrastructure Program.[71] On June 25, 2017, transportation secretary Arthur Tugade unveiled the locations of the first five stations during a press tour of the old PNR line.[72] In addition, numerous changes to the project were made. The railway's gauge was changed to standard gauge,[73] and the railway was extended to New Clark City. The south commuter line, now under the NSCR project as the North–South Commuter Railway Extension Project (NSCR-Ex),[50] shifted from a PPP scheme in favor of overseas development assistance from Japan and later the Asian Development Bank (ADB).[74] The long-haul segment of the south line was separated under a new project known as the PNR South Long Haul.

On January 21, 2019, a loan agreement worth (US$1.54 billion) for the NSCR-Ex, which includes the PNR Clark 2 and Calamba sections, was signed by JICA and the Department of Finance (DOF).[75] Another loan agreement worth (US$1.3 billion) for the NSCR-Ex project was signed on July 11 by the ADB and DOF.[76] JICA would finance the electrical and mechanical systems as well as the trains for the PNR Clark 2 and Calamba sections, while ADB would finance the civil works.[77]

The loan for the civil works of PNR Calamba, worth (US$4.3 billion), was approved by the ADB on June 9, 2022.[78] The loan agreement was signed by President Duterte and ADB on June 16.[79] Two more loan agreements were signed on February 9, 2023, during the working visit of President Bongbong Marcos in Japan.[80]

Construction

List of contractors
Contract packageScope of workContractorsDate awardedNotes
Tutuban–Malolos segment (funded by JICA)
CP 01Construction of Solis–Bocaue sectionTaisei Corporation
DMCI
May 2019[81]VSL International, a subsidiary of Bouygues was appointed as the subcontractor for the construction of the viaduct.[82]
colspan=2The Taisei-DMCI joint venture (TDJV) was originally awarded as the contractor for the segment before it was descoped as part of its revisions.[83] However, the joint venture withdrew from that segment of the contract in May 2023 due to right of way issues.[84] As of 2026, there has been no progress on this project's section.
CP 02Construction of Bocaue–Malolos sectionSumitomo Mitsui Construction[85]January 2019
CP 03Rolling stock for Tutuban–Malolos railwaySumitomo Corporation
J-TREC
July 2019
CP 04[86]Electrical and mechanical (E&M) systemsHitachi Rail STSNovember 2022[87]
CP 05Construction of Tutuban–Solis sectioncolspan=2Bidding ongoing,[88] but as of 2026, there has been no progress on this project's section.
Malolos–Clark Railway (civil works funded by ADB)
CP N-01Construction of Malolos–San Simon sectionMegawide Construction Corporation
Hyundai Engineering & Construction
Dong-ah Geological Engineering Company
September 2020[89][90]
CP N-02Construction of Santo Tomas–San Fernando, Pampanga sectionAcciona
DL E&C
October 2020[91]
CP N-03Construction of Mexico–Clark (Mabalacat) sectionItalian-Thai Development Public Company Limited
CP N-04Construction of Clark (Mabalacat)–Clark International Airport sectionEEI Corporation
Acciona
August 2020[92]
CP N-05Construction of 33-hectare (82-acre) depot and main operations control center in MabalacatPOSCO
CP S-01Construction of Solis–Blumentritt section (Blumentritt extension)PT Adhi Karya
PT PP
February 2023[93][94]
South Commuter Railway (civil works funded by ADB)
CP S-02Construction of Blumentritt–Paco sectionAcciona
DMCI
February 2023[93][95]
CP S-03aConstruction of Paco–Senate sectionLeighton Contractors (Asia)
First Balfour
June 2023[96]
CP S-03bConstruction of Senate–FTI section and tunneling works to Metro Manila Subway Senate stationFebruary 2023[97]
CP S-03cConstruction of FTI–Sucat sectionPT Adhi Karya
PT PP
June 2023[98]
CP S-04Construction of Sucat–San Pedro sectionHyundai Engineering & Construction
Dong-ah Geological Engineering Company
September 2022[99][100]
CP S-05Construction of San Pedro–Cabuyao sectionSeptember 2022[99][101]
CP S-06Construction of Cabuyao–Calamba sectionSeptember 2022[99][102]
CP S-07Construction of Banlic depotLotte Engineering & Construction
Gülermak
EEI Corporation
September 2022[99][103]
Other associated contracts (funded by JICA)
CP NS-01Electrical and mechanical (E&M) systems for Malolos–Clark and Manila–Calamba railwaysMitsubishi Corporation
Alstom
Colas Rail
February 2023[104]
CP NS-02Commuter rolling stock for Malolos–Clark and South Commuter railwaysSumitomo Corporation
J-TREC
January 2022[105][106]
CP NS-03Limited express trainsMitsubishi Corporation
Construcciones y Auxiliar de Ferrocarriles
October 2023[107]

Construction was planned to begin in the last quarter of 2017,[72] but pre-construction works, such as clearing of the right of way, were only started on January 5, 2018.[108] The railway is being built in three phases and divided into two primary sections:

  • PNR Clark — This is the northern section of the NSCR. Construction was divided into two phases. PNR Clark 1 involves the 38-kilometer (24-mile) Tutuban–Malolos railway, while PNR Clark 2 involves the 53-kilometer (33-mile) Malolos–Clark railway. The 91-kilometer (57-mile) railway line, when fully completed, will run from Tutuban station in Manila to New Clark City station within the Clark Freeport and Special Economic Zone, with a link to Clark International Airport.[109][110][111]
  • PNR Calamba — Also known as PNR Clark Phase 3,[112] PNR Calamba is the southern section of the NSCR. It involves the reconstruction of the existing Metro Commuter Line as an electrified standard gauge railway with elevated, at-grade, and depressed sections.[113][114] The 56-kilometer (35-mile) railway will run from Solis station in Manila to Calamba station in Laguna.

PNR Clark 1 broke ground on February 15, 2019,[14] followed by PNR Clark 2 on September 18, 2021.[77] Meanwhile, construction of PNR Calamba began on July 3, 2023, following the closure of Alabang–Calamba commuter services the previous day.[115] To fast-track the construction of NSCR South, the rest of the Metro Commuter Line services temporarily closed on March 27, 2024. The closure would fast-track construction by eight months, saving in costs.[116]

On March 15, 2024, the Department of Transportation announced the completion of the 14 kilometers (8.7 mi) segment of PNR Clark 1 from to . Nevertheless, the remaining segments are 37.30-percent complete as of the month, while PNR Clark 2 is at 25.76 percent.[117]

The partial opening was initially set for 2022, but this deadline was not met, presumably due to several factors including but not limited to right of way acquisition, and the COVID-19 pandemic.[118][119] Instead, it expects partial operations by December 2027 and full operations by January 2032. Additionally, according to a source, there are challenges regarding right of way, particularly in the Valenzuela to Sucat, Parañaque segment.[120] The government has extended financial help to formal and informal settlers affected by the construction.[121] However, sources said that this project couldn't be finished during the Marcos administration.[122]

The first section of the PNR Clark 1, from Solis to Valenzuela, has been postponed due to right of way issues. The right of way is obstructed by 1,100 square metres (0.00042 sq mi) of private properties, utilities, ROW sharing between the DOTr and the NLEX Harbor Link Segment 10, and affected PNR Facilities, among others. The Department of Transportation is currently unable to turn over the Caloocan depot.[84] In March 2025, PNR General Manager Deovanni Miranda stated that the segment between Tutuban and Caloocan, where informal settlers will be displaced, is under discussion with the local government. Additionally, he mentioned that the PNR area has also been 80% cleared, with the contractor expected to achieve 100% clearance.[123] As of 2026, a segment has not yet started construction.

As of January 9, 2026, the right-of-way for the NSCR is now 56% acquired, while the Metro Manila Subway right-of-way is now 90.76% acquired.[124]

Route

The North–South Commuter Railway will comprise two sections corresponding to the Philippine National Railways' old main lines. The first is the 91-kilometer (57-mile)[125] fully-elevated PNR Clark which is being built over the mostly-defunct North Main Line in northern Metro Manila and Central Luzon.[126][127] The second is the 56-kilometer (35-mile)[125] PNR Calamba which will use the existing PNR Metro Commuter Line right of way between Tutuban and Calamba, which were historically parts of the South Main Line and will have elevated, at-grade and depressed sections.[113]

Timeline of the opening of sections[128]
Date openingSegmentStations
December 2027Partial operations of Tutuban to Malolos segment
October 2028Malolos–Clark Railway Project
January 2032South Commuter Railway Project
Remaining portion of the Tutuban to Malolos segment

Services

There are four classes of services on this line. The following are:[50]

  • Commuter is the basic commuter rail service and has the least priority. It stops at all stations within its route. There are three routes planned for this class; Tutuban–New Clark City, Tutuban–Calamba, and Clark International Airport–Calamba. The maximum speed for this service will be 120 kilometers per hour (75 miles per hour) for the entire line.
  • Commuter Express is the limited-stop service for the line, succeeding the Commex service during the Metrotren era in the early 2000s. Although it will run faster than regular commuter trains, it will still use the same routes and rolling stock.
  • The Airport Limited Express is the temporary designation for the planned airport rail link and limited express service between Clark International Airport and Alabang station. As the flagship NSCR service, it will use dedicated rolling stock complete with intercity-grade amenities plus baggage space for people arriving from the airport. It will have a maximum speed of 160 kilometers per hour (100 miles per hour) along the NSCR North. As of January 2022, the final name for the service is yet to be determined.
  • Subway through-service is the proposed augmentation between the NSCR and the Metro Manila Subway. It will serve the southernmost areas of Metro Manila and neighboring Laguna, branching from the subway line at FTI station while the remainder of the line will go towards the direction of NAIA Terminal 3 in Pasay. It will use the Subway trainsets instead of the NSCR ones, although both are from the sustina family.

Stations

Proposed train stations and services[129][50][130]
PhaseStationServicesTransfersLocation
CommuterCommuter expressLimited expressThrough service to/from
Metro Manila Subway[50]
NCC–TutubanCIA–CalambaTutuban–CalambaNCC–TutubanCIA–CalambaTutuban–CalambaCity / municipalityProvince
PNR Clark 2rowspan="22"rowspan="22"rowspan="31"CapasTarlac
Clark International AirportMabalacatPampanga
rowspan="5"
Angeles City
San Fernando
Apalit
CalumpitBulacan
MalolosRobinson's MalolosMalolos
PNR Clark 1
Malolos South
Jeepneys and TricyclesGuiguinto
TuktukanTricycles
UltraMega BalagtasBalagtas
Wakas (Joner's Supermart)Bocaue
Tabing IlogMarilao
SM Marilao
Malhacan RoadMeycauayan
MalandayValenzuelaMetro Manila[note 11]
Valenzuela Polo
'LetreMalabon
5th AvenueCaloocan

Abad Santos
Manila
'
Divisoria
PNR Calambarowspan="19"rowspan="19"
Blumentritt
España
Blumentritt Road
San Diego Street

Pureza
Pasig River Ferry Service PUP Ferry Station
PacoPandacan
Taft Avenue
Buendia
Makati

Magallanes
Senate–DepEd[131][132]Taguig

TITX

Bicutan
Parañaque
PNR Bicol
Sucat
Muntinlupa
Vista Terminal Exchange
rowspan="8"Tunasan
United BayanihanSan PedroLaguna
PacitaPacita Terminal
Biñan Bayan
Southwoods
Biñan
Balibago (Santa Rosa Commercial Complex)Santa Rosa
Jeepneys and TricyclesCabuyao
PNR BicolCalamba
Stations in italics will open in 2030.

Extensions and additional stations

The Metro Manila Dream Plan proposed a 38-kilometer (24-mile) branch line that will split in Angeles City. The line will have 12 stations and shall end in Tarlac City.[133] The study also proposed a 47-kilometer (29-mile) extension of the NSCR to Batangas City.[133] This will be built parallel to the PNR South Long Haul project which was approved in 2017, with the line being a single-track, standard gauge line without electrification, and will be built at-grade similar to the present PNR network.[134] The PNR has also requested for a feasibility study for a commuter line connecting Tarlac City and San Jose, Nueva Ecija in 2019. The length of the line and the number of stations will be determined once a proposal has been submitted.[135] Another proposed southward extension to Pansol in Calamba, Laguna was proposed by a 2019 JICA report.[136]

The North–South Commuter Railway will also have provisions for infill stations: Malabon, Valenzuela Polo, Tabing Ilog, Tuktukan, and Malolos South.[50]

In response to the difficulties of the right of way acquisition, shuttle services can bring commuters from West Valenzuela station to Tutuban.[137]

Infrastructure

NSCR will be the first commuter rail system in the country to be mostly grade-separated. Trains are designed to run on tracks at a design speed of 120 kilometers per hour (75 miles per hour) for regular trains and 160 kilometers per hour (99 miles per hour) for airport express trains.[138]

Station layout

All stations will have a standard layout, with a concourse level and a platform level. The stations are designed to adhere to both Philippine and Japanese standards.[50] Stations will either have island platforms or side platforms with platform screen doors. The stations are designed to be barrier-free, and trains shall have spaces for passengers using wheelchairs. Historical stations will be preserved.[139] All stations will have access to intermodal facilities.[50] The FTI station in particular will be connected to the Taguig Integrated Terminal Exchange.[140]

Rolling stock

The North–South Commuter Railway will have two types of rolling stock: commuter trains and airport express trains. Except for wheelchair spaces, the commuter trains will have a capacity of 2,242 passengers. The express trains, on the other hand, will have a capacity of 392 passengers.[141] A total of 464 electric multiple unit traincars have been procured to operate on the line, with 408 of these being the 8-car EM1000 class trainsets to be built by the Japan Transport Engineering Company (J-TREC), successor to the Tokyu Car Corporation that provided rolling stock to the Philippines from 1955 to 1976. The trainsets, called the Sustina Commuter at the time of purchase, are based on JR East commuter stock such as the E233 series but adapted to standard gauge. The trains are also designed to be interoperable with the Metro Manila Subway.[142] The trainsets have been designated as the EM1000 class in October 2021.[143]

The procurement for the 56 airport express trainsets began on February 26, 2021, with a suggested preliminary design based on the E259 and E353 series being published on the same day.[141] On May 10, the Department of Transportation later announced that it would acquire the airport express trainsets from Japanese manufacturers.[144] After several months of delays and rescheduling, three bidders have submitted their designs on October 15: Kawasaki Heavy Industries and Sojitz, Marubeni and Stadler Rail, and Mitsubishi and Construcciones y Auxiliar de Ferrocarriles (CAF).[145] On August 24, 2023,[146] Mitsubishi and CAF, also the manufacturers of the LRTA 13000 class trains on the LRT Line 1, were awarded the contract for the express trains.[107]

Rolling stockCommuter trains[50][147][1]Airport express trains[141][148]
Image
YearBatch 1: Fiscal 2022
Batch 2: 2025–2028[149]
TBD
ManufacturerJ-TRECMitsubishi and CAF
ModelEM1000 classEM000000 class
Number to be built408 cars (51 sets)56 cars (7 sets)
Order no.CP 03 (first batch)
CP NS-02 (second batch)
CP NS-03
Formation8 cars per trainset
Car length20 m (65 ft 7 in)
Width2.95 m (9 ft 8 in)
height4.15 m (13 ft 7 in)
Floor height1.13–1.15 m ftin
Body materialLightweight stainless steelAluminum alloy and stainless steel
Tare weight270 t (600,000 lb)315 t (694,000 lb)
Axle load16 t (35,000 lb)
CapacityLeading car: 266 standing, 45 seated
Intermediate car: 285 standing, 54 seated
Leading car: 40 seated
Intermediate car: 52 seated
PWD seating: 8 wheelchair spaces
Seat layoutRapid transit-style longitudinal seatingAirline-style open coach seating
Doors per side42
Traction controlIGBTVVVF (first batch)
Hybrid SiCVVVF (second batch)
Hybrid SiCVVVF
Traction poweroverhead catenary
Pantograph type1 single-arm pantographToyo Denki 2 single-arm pantographs, outward facing
Top speed120 km/h (75 mph)≥170 km/h (110 mph)
Train configuration––M––T–M–M–TcTc–M–M–M–M–M–M–Tc
Other featuresToilets, luggage racks
Status

Signaling

The North–South Commuter Railway will use the European Train Control System (ETCS) Level 2 for signaling, making it the first main line in Southeast Asia with ETCS Level 2.[150] Initially, the PNR Clark 1 section of the line was set to use a communications-based train control (CBTC) system.[147] The subsystems consist of automatic train control (ATC), automatic train protection (ATP), automatic train supervision (ATS), train detection through track circuits, and computer-based interlocking, with provisions for automatic train operation (ATO).[151]

Hitachi Rail STS, Hitachi's Italian subsidiary, was tapped in November 2022 to provide the signaling equipment for PNR Clark 1 as part of a contract package covering electrical and mechanical systems, and track works.[87] Meanwhile, Alstom was tapped in March of the same year to supply its Atlas 200 solution for PNR Clark 2 and PNR Calamba.[150]

Tracks

The line will feature an Elastic Sleeper Direct Fasten (ESDF) type ballastless track with concrete sleepers in the mainline and plastic/fiber-reinforced foam urethane railroad ties on turnouts in the mainline and depot.[151] Continuous welded rails will be employed on the mainline, while jointed rails with fishplates will be employed in the depot. 60-kilogram per metre (40-pound per foot) rails will be employed in the mainline while rails built to the JIS 50N rail profile will be used in the depot.[151]

Depot

The railway will have three depots with one in each region: Malanday, Mabalacat, and Banlic.[152] The Malanday depot, located beside the Valenzuela station in Malanday, Valenzuela, will serve as the main depot, hosting the operations control center for the entire line.[153] The Mabalacat depot, located along Gil Puyat Avenue in Clark Freeport Zone, Mabalacat, Pampanga, will function as a parking facility for train sets plying the Malolos–Calamba route.[154] The Banlic depot will be located on a 24.5-hectare (61-acre) lot in Calamba, Laguna, near the namesake barangay and station in Cabuyao, featuring a control center, stabling yard, maintenance shop, and ancillary buildings.[155][156]

See also

Notes

  1. ^ The project will be implemented in three phases, which will have their own opening dates.
  2. ^ Main depot
  3. ^ May be through viaduct or embankment. Also includes an at-grade section between EDSA and FTI stations and an underground section around Clark International Airport station.
  4. ^ May use quadruple-track at stations.
  5. ^ Hitachi Rail STS will supply ETCS Level 2 equipment along Phase 1 between Tutuban and Malolos,[87] while Alstom's Atlas 200 was selected for the Malolos–Clark and NSCR South segments.[104][150]
  6. ^ Tagalog: Daambakal Pangmananakay na Pahilaga–Timog; pam: Dalang Bakal ning Pamanyakeng Papangulu–Mauli
  7. ^ Segment is covered by the Northrail–Southrail Linkage, of which only the segment from Caloocan to Alabang was completed.
  8. ^ Segment is covered by the PNR North Long Haul.
  9. ^ Segment is covered by the Subic–Clark Railway.
  10. ^ Segment is covered by the PNR Northeast Commuter Line.
  11. ^ Metro Manila is not a province, but a metropolitan area and region.

References

  1. ^ PART 2 - EMPLOYER'S REQUIREMENTS from BIDDING DOCUMENTS FOR PROCUREMENT OF PACKAGE CP NS-02: ROLLING STOCK - COMMUTER TRAINSETS. Vol. 2 of 3. Philippine National Railways. September 2020. Archived January 4, 2022 at the Wayback Machine. Retrieved January 4, 2022.
  2. ^ Main Points of the Roadmap. Japan International Cooperation Agency. September 2014. Archived from the original on 2014-10-11.
  3. ^ Camus, Miguel R. (February 16, 2019). "DOTr plans to integrate new railway lines". business.inquirer.net. Archived February 16, 2019 at the Wayback Machine. Retrieved February 16, 2019.
  4. ^ Pateña, Aerol John (April 30, 2019). "DOTr awards contract to DMCI Consortium for PNR North Phase 1 Project". Philippine News Agency. Archived November 11, 2020 at the Wayback Machine. Retrieved May 27, 2021.
  5. ^ "Off track: Northrail timeline". ABS-CBN News. July 15, 2008. Archived February 17, 2019 at the Wayback Machine. Retrieved February 17, 2019.
  6. ^ Inquirer, Philippine Daily (January 17, 2019). "WHAT WENT BEFORE: The Northrail Project". newsinfo.inquirer.net. Archived February 14, 2019 at the Wayback Machine. Retrieved February 16, 2019.
  7. ^ "METRO MANILA URBAN TRANSPORTATION INTEGRATION STUDY". www.jica.go.jp. March 1999. Retrieved June 14, 2024.
  8. ^ "U.P. study finds North Rail contract illegal, disadvantageous to government". The PCIJ Blog. September 9, 2005. Archived from the original on August 12, 2014. Retrieved July 29, 2014.
  9. ^ Nicolas, Jino (2017-11-06). "Northrail dispute settled". BusinessWorld. Archived June 26, 2021 at the Wayback Machine. Retrieved 2021-06-26.
  10. ^ Reyes, Miguel Paolo P. "It's Not You, It's Me? An Inquiry into the Problems of Philippine-Korean Cooperation for Metro Manila's Rail-based Mass Transit Systems". The Mass Transit System in Metro Manila: From Tranvia to MRT, 1879-2014. University of the Philippines Diliman. Retrieved May 29, 2024.
  11. ^ Reyes, Miguel Paolo P. "It's Not You, It's Me? An Inquiry into the Problems of Philippine-Korean Cooperation for Metro Manila's Rail-based Mass Transit Systems". The Mass Transit System in Metro Manila: From Tranvia to MRT, 1879-2014. University of the Philippines Diliman. Retrieved May 29, 2024.
  12. ^ "DOTC eyes elevated railway from Malolos to Los Banos". ABS-CBN News. July 22, 2013. Archived August 22, 2015 at the Wayback Machine. Retrieved April 23, 2019.
  13. ^ "Japan Commits JPY241.991 Billion ODA For North-South Commuter Railway Project (Malolos - Tutuban)". www.ph.emb-japan.go.jp (Embassy of Japan in the Philippines). 19 November 2015. Archived December 24, 2020 at the Wayback Machine. Retrieved 24 December 2020.
  14. ^ Mercurio, Richmond (February 16, 2019). "Construction of North-South Commuter Railway kicks off". Philstar.com. Archived September 1, 2021 at the Wayback Machine. Retrieved 2021-09-01.
  15. ^ Dela Cruz, Raymond Carl (August 11, 2022). "DOTr assures North-South Commuter Railway on-time completion". Philippine News Agency. Retrieved November 30, 2022.
  16. ^ "Economy and Dev't Council approves PPP for North-South Commuter Railway operations". ABS-CBN News. 2025-07-16. Retrieved 2025-07-17.
  17. ^ "Study on Railway Strategy for Clark-Metro Manila for the Greater Capital Region in the Republic of the Philippines: Final Report". www.jica.go.jp. June 2013. Retrieved June 14, 2024.
  18. ^ Orbon, Glenn & Dungca, Joana (2015). "The Philippine Railway System". Movement Systems
  19. ^ Gamble, Adrian (March 10, 2017). "Manila's Long-Lost 'Tranvias' Once the Envy of Asia". skyrisecities.com. Skyrise Cities. Archived June 21, 2020 at the Wayback Machine. Retrieved June 21, 2020.
  20. ^ "Chapter I: Present Conditions". Report of Survey of the Manila Railroad Company and the Preliminary Survey of Railroads for Mindanao. Chicago: De Leuw, Cather & Company. 1951. pp. 1–12.
  21. ^ "Republic Act No. 4156 | GOVPH". Official Gazette of the Republic of the Philippines. Archived 2022-01-03 at the Wayback Machine. Retrieved 2022-01-03.
  22. ^ "Carmona's Commuter Train". Times Journal. April 1973. Archived July 13, 2021 at the Wayback Machine. Retrieved July 23, 2020.
  23. ^ "Brief history of PNR". Philippine National Railways (February 27, 2009). Archived from the original on February 27, 2009. Retrieved November 4, 2011.
  24. ^ "REPORT ON STUDY OF THE ELECTRIFICATION OF THE PNR COMMUTER SERVICE". Japanese International Cooperation Agency (JICA). December 1978. Archived May 22, 2021 at the Wayback Machine. Retrieved February 15, 2021.
  25. ^ "Metrotren Inaugural". Manila Chronicle. May 11, 1990. Archived July 13, 2021 at the Wayback Machine. Retrieved May 6, 2021.
  26. ^ "Corporate Profile". Philippine National Railways. Archived 2022-01-03 at the Wayback Machine. Retrieved 2022-01-03. The PNR currently operates in the Manila metropolitan area and the provinces of Laguna, Quezon, Camarines Sur and Albay. In the past, the PNR also used to serve the provinces of Bulacan, Pampanga, Tarlac, Nueva Ecija, Pangasinan and La Union on the North Main Line, and Batangas on the South Main Line.
  27. ^ "Executive Order No. 174". Jur
  28. ^ "G.R. No. 173137"
  29. ^ Go, Marianne V. "Northrail project to push through — Palace adviser". Philstar.com. Retrieved 2024-06-13.
  30. ^ Railway project draws the big boys. Manila Standard. January 3, 1996.
  31. ^ "Cross-Manila conflict". Railway Gazette International. September 1, 1997.
  32. ^ Go, Marianne V. "Northrail project to push through — Palace adviser". Philstar.com. Retrieved 2024-06-13.
  33. ^ "Railroading of North...". Philippine Daily Inquirer. October 18, 2004. pp. B12.
  34. ^ "Ayala may lose P18-B infra project". The Philippine Star. January 25, 2000.
  35. ^ "Gov't to tap Obuchi Fund for P18.2-B infra project". The Philippine Star. March 26, 2000. Retrieved May 12, 2024.
  36. ^ Japan to provide $300M in new loans. Philippine Daily Inquirer. April 8, 2000.
  37. ^ "Japan mulls P500-M grant for railway rehab". The Philippine Star. August 28, 2001. Retrieved May 12, 2024.
  38. ^ "The Study on the Standardization for Integrated Railway Network of Metro Manila (SIRNMM) Final Report (Summary)". March 2001. Retrieved June 14, 2024.
  39. ^ "The Study on the Standardization for Integrated Railway Network of Metro Manila (SIRNMM) Final Report (Main Report)". www.jica.go.jp. March 2001. Retrieved June 14, 2024.
  40. ^ "Study on Railway Strategy for Clark-Metro Manila for the Greater Capital Region in the Republic of the Philippines: Final Report". www.jica.go.jp. June 2013. Retrieved June 14, 2024.
  41. ^ Paz, Chrisee Dela (November 6, 2017). "PH gov't ends dispute with China's Sinomach over Northrail project". Rappler. Archived November 25, 2018 at the Wayback Machine. Retrieved February 16, 2019.
  42. ^ "RP, China break ground for Manila–Ilocos railway". Malaya. April 6, 2004. Archived from the original on May 9, 2010. – via lrta.gov.ph
  43. ^ GMANews.TV, AIE BALAGTAS SEE (2008-09-09). "Solon urges speedy modernization of PNR". GMA News Online. Retrieved 2024-06-13.
  44. ^ "Directing the Senate Blue Ribbon Committee To Conduct an Inquiry, in Aid of Legislation, Into the Alleged Overpricing of the Southrail Project, Rehabilitating the Railway System From Manila to Bicol, With the End in View of Providing Remedial Legislation That Will Further Strengthen the Pertinent Provisions of Republic Act No. 9184 or the Government Procurement Reform Act, and Republic Act No. 3019 or the Anti-Graft and Corrupt Practices Act.". Senate of the Philippines. Retrieved 2024-06-13.
  45. ^ Diaz, Jess. "JDV backs Senate probe into Southrail". Philstar.com. Retrieved 2024-06-13.
  46. ^ Files, YVONNE T. CHUA and ELLEN TORDESILLAS, VERA (2008-03-09). "6 Philippine-occupied islands covered in Spratly agreements". GMA News Online. Retrieved 2024-06-24.
  47. ^ Reyes, Miguel Paolo P. "It's Not You, It's Me? An Inquiry into the Problems of Philippine-Korean Cooperation for Metro Manila's Rail-based Mass Transit Systems". The Mass Transit System in Metro Manila: From Tranvia to MRT, 1879-2014. University of the Philippines Diliman. Retrieved May 29, 2024.
  48. ^ Estavillo, Maricel (2007-07-04). "PNR remits $14.7M to South Korean consortium". GMA News Online. Retrieved 2024-06-24.
  49. ^ "Annual Audit Report for the Philippine National Railways". Philippine National Railways. Retrieved 2024-06-13.
  50. ^ Department of Transportation The Republic of the Philippines (October 2018). "FEASIBILITY STUDY ON THE NORTH SOUTH RAILWAY PROJECT-SOUTH LINE (COMMUTER)(NORTH-SOUTH COMMUTER RAILWAY EXTENSION PROJECT) IN THE REPUBLIC OF THE PHILIPPINES". jica.go.jp. Archived April 11, 2021 at the Wayback Machine. Retrieved April 26, 2019.
  51. ^ "Philippines: China-funded Northrail project derailed". Financial Times. Archived August 17, 2018 at the Wayback Machine. Retrieved February 17, 2019.
  52. ^ Basa, Mick (August 21, 2014). "Northrail project up for NEDA-ICC approval soon". Rappler. Archived February 18, 2019 at the Wayback Machine. Retrieved February 17, 2019.
  53. ^ "付属資料 E: 施工済み構造物の転用可能" [Appendix E: Possible repurposing of already constructed structures]. Japan International Cooperation Agency. Retrieved 2024-06-13.
  54. ^ Bordadora, Norman (September 2, 2011). "China open to reconfiguring NorthRail project, says Roxas". newsinfo.inquirer.net. Archived April 1, 2019 at the Wayback Machine. Retrieved February 16, 2019.
  55. ^ Calica, Aurea. "Phl, China drop North Rail". Philstar.com. Retrieved 2024-06-18.
  56. ^ de Vera, Ben O. (December 18, 2019). "Northrail up for abolition". Philippine Daily Inquirer. Retrieved October 21, 2023.
  57. ^ Geducos, Argyll Cyrus (October 21, 2023). "Malacañang abolishes Northrail". Manila Bulletin. Retrieved October 21, 2023.
  58. ^ "DOTC eyes elevated railway from Malolos to Los Banos". ABS-CBN News. July 22, 2013. Archived from the original on August 22, 2015. Retrieved April 23, 2019.
  59. ^ "Govt eyes elevated rail project in Luzon - Manila Standard Today". Archived from the original on January 2, 2014. Retrieved January 1, 2014.
  60. ^ Main Points of the Roadmap. Japan International Cooperation Agency. September 2014. Archived from the original on October 11, 2014.
  61. ^ Rimando, Lala (2012-10-10). "DOTC still eyeing rail-over-NLEx to improve access to Clark airport". RAPPLER. Archived 2022-08-04 at the Wayback Machine. Retrieved 2024-06-18.
  62. ^ "P287-B North-South Railway project eyed for 2020 operation". PPP Center. 18 February 2015. Archived July 2, 2021 at the Wayback Machine. Retrieved 24 December 2020.
  63. ^ "NEDA Board approves six transport infra projects". www.officialgazette.gov.ph. 16 February 2015. Archived July 2, 2021 at the Wayback Machine. Retrieved 25 December 2020.
  64. ^ "Bidders line up for Philippines North-South line". International Railway Journal. 2015-08-20. Archived May 17, 2021 at the Wayback Machine. Retrieved 2021-05-17.
  65. ^ "New north-south commuter railway set". www.officialgazette.gov.ph. 1 December 2015. Archived July 2, 2021 at the Wayback Machine. Retrieved 24 December 2020.
  66. ^ "PNR lines up new railway project for PPP". Philstar.com. Retrieved 2021-11-03.
  67. ^ Camus, Miguel (29 January 2016). "PH, Japan seal P97-B commuter rail project". Philippine Daily Inquirer. Archived December 24, 2020 at the Wayback Machine. Retrieved 24 December 2020.
  68. ^ Diangson, Louie (29 January 2016). "PH, Japan signs deal for the Php97 billion commuter railway". www.yugatech.com. Archived December 24, 2020 at the Wayback Machine. Retrieved 24 December 2020.
  69. ^ Dela Paz, Chrisee (28 November 2015). "PH, Japan sign $1.99B loan for North-South commuter railway". rappler.com. Archived 25 November 2018 at the Wayback Machine. Retrieved 25 December 2020.
  70. ^ Ranada, Pia (2016-06-21). "Duterte: China offering to build Manila-Clark railway in 2 years". RAPPLER. Retrieved 2024-11-19.
  71. ^ "Tugade: PNR Clark, Calamba trains to arrive in December 2021". Philippine Information Agency. Archived June 26, 2021 at the Wayback Machine. Retrieved 2021-06-26.
  72. ^ Dela Paz, Chrisee (June 25, 2017). "17 stations of Manila–Clark railway announced". Rappler. Archived March 22, 2019 at the Wayback Machine. Retrieved February 17, 2019.
  73. ^ "Philippines adopts standard gauge for new lines". International Railway Journal. 2016-08-09. Archived April 23, 2021 at the Wayback Machine. Retrieved 2021-05-17.
  74. ^ Dela Paz, Chrisee (17 November 2016). "Duterte gov't calls off auction for South Line of North-South Railway". Rappler. Archived 2016-11-21 at the Wayback Machine. Retrieved 25 May 2022.
  75. ^ Padin, Mary Grace (January 23, 2019). "Gov't secures P98.7 billion JICA loans for railway, flood control". The Philippine Star. Archived November 26, 2020 at the Wayback Machine. Retrieved February 3, 2022.
  76. ^ Parrocha, Azer (July 11, 2019). "PRRD orders DOTr to hasten completion of Malolos-Clark Railway". Philippine News Agency. Archived July 11, 2019 at the Wayback Machine. Retrieved February 3, 2022.
  77. ^ "NSCR Extension Project starts construction". The Manila Times. 2021-09-27. Retrieved May 24, 2022.
  78. ^ de Vera, Ben O. (June 9, 2022). "ADB OKs $4.3B loan for Manila-Calamba railway project". Philippine Daily Inquirer. Retrieved June 9, 2022.
  79. ^ Pinlac, Beatrice (June 17, 2022). "PH, ADB ink $4.3B loan agreement for South Commuter Railway project". Philippine Daily Inquirer. Retrieved June 17, 2022.
  80. ^ Cordero, Ted (February 9, 2023). "PH, Japan ink ¥400-B loan deals for North-South railway, extension projects". GMA Integrated News. Retrieved February 22, 2023.
  81. ^ "DMCI, Japanese partner bag P54-B contract for North-South Commuter Railway project". GMA News Online. May 21, 2019. Archived May 28, 2019 at the Wayback Machine. Retrieved May 28, 2019.
  82. ^ "Viaduct contract awarded for Philippines' NSCR". International Railway Journal. 2020-12-22. Archived May 17, 2021 at the Wayback Machine. Retrieved 2021-05-17.
  83. ^ "DMCI sees signs of recovery in construction business". Manila Bulletin. Retrieved 2024-06-20.
  84. ^ Cordero, Ted (30 May 2023). "DOTr, DMCI-Taisei withdraw from Section 1 of North-South railway contract package 1". GMA Integrated News. Retrieved 30 May 2023.
  85. ^ "Overview". Sumitomo Mitsui Construction. February 10, 2021. Retrieved May 25, 2022.
  86. ^ "NORTH-SOUTH COMMUTER RAILWAY PROJECT (MALOLOS-TUTUBAN) N1CP04: ELECTRICAL AND MECHANICAL SYSTEMS AND TRACKWORKS". Department of Transportation (Philippines). August 25, 2021. Archived from the original on November 5, 2021. Retrieved November 5, 2021.
  87. ^ Balinbin, Arjay L. (2022-11-14). "Malolos-Tutuban rail contract bagged by Japan's Hitachi Rail". BusinessWorld. Retrieved 2022-11-22.
  88. ^ Procurement Service – Philippine Government Electronic Procurement System (2022-10-13). "General Bid Bulletin No. 4 - Responses to Clarifications". Retrieved 2023-02-21.
  89. ^ Manuel, Pilar (September 21, 2020). "Megawide, 2 Korean firms secure construction for part of Malolos-Clark Railway". CNN Philippines. Archived from the original on October 18, 2020. Retrieved May 5, 2021.
  90. ^ Loyola, James A. (September 21, 2020). "Megawide, Korean partners win P28-B railway project". Manila Bulletin. Archived July 2, 2021 at the Wayback Machine. Retrieved May 5, 2021.
  91. ^ "Contracts Worth $1.7 Billion Awarded for ADB-Funded Malolos–Clark Railway Project". Asian Development Bank. 2020-10-08. Archived 2022-01-03 at the Wayback Machine. Retrieved 2022-01-03.
  92. ^ "Philippines awards North-South Commuter Railway contracts". International Railway Journal. 2020-08-04. Archived May 17, 2021 at the Wayback Machine. Retrieved 2021-05-17.
  93. ^ Rosales, Elijah Felice (2023-02-21). "DOTr awards contract for P40 billion NSCR line". Philstar. Retrieved 2023-02-21.
  94. ^ Department of Transportation (2023-02-17). "Notice of Contract Award: Malolos to Clark Railway Project (Blumentritt Extension) - Package CP S-01". Procurement Service – Philippine Government Electronic Procurement System. Retrieved 2023-02-21.
  95. ^ Department of Transportation (2023-02-17). "Notice of Contract Award: South Commuter Railway Project - Package CP S-02". Procurement Service – Philippine Government Electronic Procurement System. Retrieved 2023-02-21.
  96. ^ Department of Transportation (2023-06-26). "Notice of Contract Award: South Commuter Railway Project - Package CP S-03A". Procurement Service – Philippine Government Electronic Procurement System. Retrieved 2023-06-26.
  97. ^ Department of Transportation (2023-02-20). "Notice of Contract Award: South Commuter Railway Project - Package CP S-03B". Procurement Service – Philippine Government Electronic Procurement System. Retrieved 2023-02-21.
  98. ^ Department of Transportation (2023-06-26). "Notice of Contract Award: South Commuter Railway Project - Package CP S-03C". Procurement Service – Philippine Government Electronic Procurement System. Retrieved 2023-06-26.
  99. ^ "4 North-South Railway contracts awarded". PortCalls Asia. October 6, 2022. Retrieved October 6, 2022.
  100. ^ Department of Transportation (2022-09-23). "Notice of Contract Award: South Commuter Railway Project - Package CP S-04". Procurement Service – Philippine Government Electronic Procurement System. Retrieved 2023-02-21.
  101. ^ Department of Transportation (2022-09-23). "Notice of Contract Award: South Commuter Railway Project - Package CP S-05". Procurement Service – Philippine Government Electronic Procurement System. Retrieved 2023-02-21.
  102. ^ Department of Transportation (2022-09-23). "Notice of Contract Award: South Commuter Railway Project - Package CP S-06". Procurement Service – Philippine Government Electronic Procurement System. Retrieved 2023-02-21.
  103. ^ Department of Transportation (2022-09-23). "Notice of Contract Award: South Commuter Railway Project - Package CP S-07". Procurement Service – Philippine Government Electronic Procurement System. Retrieved 2023-02-21.
  104. ^ Department of Transportation (February 2, 2023). "Notice of Award". Department of Transportation (Philippines). Retrieved February 8, 2023.
  105. ^ Department of Transportation (2022-01-14). "Notice of Award of Contract Package NS-02: Rolling Stock – Commuter Trainsets". Procurement Service – Philippine Government Electronic Procurement System. Retrieved 2023-02-21.
  106. ^ Balinbin, Arjay (2022-03-09). "Japan's J-Trec-Sumitomo JV bags new trainset contract for gov't railways". BusinessWorld. Retrieved 2023-02-21.
  107. ^ Rosales, Elijah Felice (October 10, 2023). "Mitsubishi bags P9 billion airport train deal". Philstar. Retrieved October 10, 2023.
  108. ^ Pateña, Aerol John (January 6, 2018). "Preps begin for Phase 1 of PNR Clark railway project". Philippine News Agency. Archived June 26, 2021 at the Wayback Machine. Retrieved 2021-06-26.
  109. ^ Dela Paz, Chrisee. "17 stations of Manila–Clark Railway revealed". Rappler. Archived March 22, 2019 at the Wayback Machine. Retrieved June 25, 2017.
  110. ^ Aning, Jerome (June 25, 2017). "DOTr leads marking of Manila–Clark railway's 5 future stations". Philippine Daily Inquirer. Archived June 12, 2018 at the Wayback Machine. Retrieved June 25, 2017.
  111. ^ "PH, Japan sign P78-b loan for Luzon railway network". Manila Standard. Archived November 25, 2018 at the Wayback Machine. Retrieved February 17, 2019.
  112. ^ "DOTr - TUGADE: PNR CLARK, CALAMBA TRAINS TO ARRIVE IN DECEMBER 2021". dotr.gov.ph. Archived June 2, 2021 at the Wayback Machine. Retrieved 2021-07-13.
  113. ^ Dela Paz, Chrissie (September 13, 2017). "NEDA Board approves Manila subway, longest railway". Rappler. Archived September 14, 2017 at the Wayback Machine. Retrieved September 15, 2017.
  114. ^ Leyco, Chino S. (September 13, 2017). "NEDA Board approves big infra projects". Manila Bulletin. Archived from the original on September 14, 2017. Retrieved September 15, 2017.
  115. ^ Abadilla, Emmie V. (July 3, 2023). "P73-B Alabang-Calamba leg of NSCR breaks ground". Manila Bulletin. Retrieved July 24, 2023.
  116. ^ Yu, Lance Spencer (March 8, 2024). "PNR will stop operations on March 28 for five years". Rappler. Retrieved March 25, 2024.
  117. ^ De Leon, Jovi (March 15, 2024). "DOTr: Malolos-Bocaue NSCR viaduct finished". SunStar. Retrieved March 17, 2024.
  118. ^ Gines, Ben Jr. (2021-12-02). "PNR phase 1 on track for 2022 completion". The Manila Times. Archived 2021-12-02 at the Wayback Machine. Retrieved 2022-01-03.
  119. ^ "LOOK: PNR Clark phase 2 train will run from Malolos to Clark in 30 minutes | Coconuts". Coconuts Manila. 2021-09-21. Archived 2021-09-23 at the Wayback Machine. Retrieved 2022-01-03.
  120. ^ Hilotin, Jay (2025-09-08). "Philippines: $15.4-billion North-South Commuter Railway to beat Manila's traffic nightmare?". Gulf News: Latest UAE news, Dubai news, Business, travel news, Dubai Gold rate, prayer time, cinema. Retrieved 2025-10-26.
  121. ^ Nicolas, Jino (2024-09-19). "ROW issues cause a major hurdle in the NSCR completion - PNR". BusinessWorld Online. Retrieved 2024-09-26.
  122. ^ "Metro Manila Subway partial operations likely by 2032 - DOTr". ABS-CBN News. March 19, 2025.
  123. ^ Department of Transportation - Philippines (2025-04-04). DOTr SAKAY NA! sa Radyo Pilipinas ep. 12 - PNR [03/26/2025]. Retrieved 2025-07-16. – via YouTube.
  124. ^ Argosino, Faith (2026-01-09). "DOTr reports major gains in land acquisition for subway, NSCR projects". INQUIRER.net. Retrieved 2026-02-17.
  125. ^ "Civil works start for Metro Manila-Bulacan railway segment". www.pna.gov.ph. Archived June 3, 2020 at the Wayback Machine. Retrieved January 22, 2020.
  126. ^ "Project_Details – BUILD". build.gov.ph. Archived August 14, 2020 at the Wayback Machine. Retrieved April 27, 2019.
  127. ^ "Project Details – Build". Build.gov.ph. June 1, 2018. Retrieved January 9, 2020.[dead link]
  128. ^ "North-South Commuter Railway Operations and Maintenance PPP Project - Market Sounding Roadshow". PPP Center
  129. ^ Ruby. "Railways Sector". www.dotr.gov.ph. Department of Transportation (Philippines). Archived May 26, 2021 at the Wayback Machine. Retrieved June 10, 2021.
  130. ^ "Chapter 6". Route Plan and Railways System. Study on railway strategy for Clark-metro Manila for the greater capital region in the Republic of the Philippines: final report.. Vol. II. Japan International Cooperation Agency. June 2013. Retrieved September 11, 2021.
  131. ^ "Philippines: South Commuter Railway Project". Asian Development Bank. May 2022. Retrieved October 20, 2022.
  132. ^ "Invitation for Bids, PB21-036-5". South Commuter Railway Project for Package Number CP S-03a: Building and Civil Engineering Works for approximately 7.9 kms of at Grade and Viaduct Railway Track Structure including Elevated Station at Buendia and at Grade Stations at EDSA and Senate. March 22, 2021. Retrieved October 20, 2022.
  133. ^ "Roadmap for Transport Infrastructure Development for Metro Manila and its Surrounding Areas (Region III and Region IV-A)". Japan International Cooperation Agency. March 30, 2014. Archived June 27, 2020 at the Wayback Machine. Retrieved May 7, 2020.
  134. ^ Dela Paz, Chrisee (September 13, 2017). "NEDA Board approves Metro Manila Subway". Rappler. Archived September 14, 2017 at the Wayback Machine. Retrieved September 14, 2017.
  135. ^ Villanueva, Joann (January 22, 2019). "PNR asks for feasibility of Cabanatuan-Makati line". Philippine News Agency. Archived November 5, 2020 at the Wayback Machine. Retrieved August 2, 2020.
  136. ^ National Economic and Development Authority (August 2019). FOLLOW-UP SURVEY ON ROADMAP FOR TRANSPORT INFRASTRUCTURE DEVELOPMENT FOR GREATER CAPITAL REGION (GCR). Vol. JR 19-003. Japan International Cooperation Agency
  137. ^ "Facebook post"
  138. ^ "North-South Railway Project, Philippines". railway-technology. April 16, 2024. Retrieved June 18, 2024.
  139. ^ INQUIRER.net (June 4, 2019). "PNR to preserve old train stations in Bulacan". newsinfo.inquirer.net. Archived July 27, 2020 at the Wayback Machine. Retrieved April 18, 2020.
  140. ^ Pateña, Aerol John (January 18, 2018). "Taguig integrated terminal to ease traffic on EDSA". Philippine News Agency. Archived 2022-01-03 at the Wayback Machine. Retrieved 2022-01-03.
  141. ^ BIDDING DOCUMENTS FOR PROCUREMENT OF PACKAGE CP NS-03: ROLLING STOCK - LIMITED EXPRESS TRAINSETS. Vol. 2 of 3. Philippine National Railways. February 2021. Archived August 21, 2021 at the Wayback Machine. Retrieved August 19, 2021.
  142. ^ Balinbin, Arjay L. (July 21, 2021). "North-South rail, subway trains to start arriving in December". BusinessWorld. Archived July 21, 2021 at the Wayback Machine. Retrieved July 23, 2021.
  143. ^ マニラ南北線EM10011Mとマニラ南北線EM10011Lが株式会社総合車両製作所(J-TREC)から陸送!【令和3年(西暦2021年)10月18日月曜日】 [Manila North-South Line EM10011M and Manila North-South Line EM10011L being shipped by land from [the] Japan Transport Engineering Company (J-TREC)! (Monday, October 18, 2021)] (YouTube) (in Japanese). October 18, 2021. Retrieved October 19, 2021.
  144. ^ "Philippines: Philippines to engage Japanese manufacturers for NSCR Express trainsets". International Union of Railways. May 10, 2021. Archived May 17, 2021 at the Wayback Machine. Retrieved May 17, 2021.
  145. ^ LIVE: Bid Opening for the Contract Package NS-03 - Limited Express Rolling Stock (Facebook Live) (16:9 720p). Department of Transportation (Philippines). October 15, 2021. Retrieved October 16, 2021.
  146. ^ "Letter of Acceptance". 24 August 2023. Retrieved 27 June 2024.
  147. ^ BIDDING DOCUMENTS FOR THE PROCUREMENT OF PACKAGE CP03: ROLLING STOCK. Vol. 2 of 3. Department of Transportation (Philippines). July 2018. Archived January 4, 2022 at the Wayback Machine. Retrieved January 4, 2022.
  148. ^ Valdez, Denise (July 17, 2019). "DoTr, Japan firms ink P12-B contract for train cars". BusinessWorld. Archived April 14, 2021 at the Wayback Machine. Retrieved April 14, 2021.
  149. ^ "Order Received to Supply 304 for the Philippines' North-South Commuter Railway Extension Project". Sumitomo Corporation. 2022-03-18. Archived 2022-03-20 at the Wayback Machine. Retrieved 2022-03-20.
  150. ^ "Alstom-led consortium to provide integrated railway system for the Philippines' North-South Commuter Railway Extension Project". Alstom. March 6, 2022. Retrieved March 7, 2022.
  151. ^ "PART 2 Employer's Requirements". The Malolos–Clark Railway Project and the North South Railway Project-South Line (Commuter) PACKAGE CP NS-01: E&M SYSTEMS AND TRACK WORKS. Vol. 2. Department of Transportation (Philippines). March 2021. Archived 2022-03-13 at the Wayback Machine. Retrieved 2022-03-13.
  152. ^ Taguines, Andrea (June 13, 2024). "North-South Commuter Railway partial operations pushed back to 2027: DOTr". ABS-CBN News. Retrieved September 24, 2024.
  153. ^ Jose, Ashley Erika O. (July 18, 2024). "NSCR Bulacan station nearing completion". BusinessWorld. Retrieved September 24, 2024.
  154. ^ Vicencio, Lady (August 12, 2024). "Privatization eyed for Metro Manila Subway, North-South Commuter Railway". ABS-CBN News. Retrieved September 24, 2024.
  155. ^ Dela Cruz, Raymond Carl (June 13, 2024). "DOTr begins work on NSCR Banlic Depot in Calamba". Philippine News Agency. Retrieved September 24, 2024.
  156. ^ Jose, Ashley Erika O. (June 13, 2024). "Construction starts on NSCR Calamba depot". BusinessWorld. Retrieved September 24, 2024.